- The new stairs have been installed. The stair guy just needs to finish some small details.
- My friend Ross (a veritable metal wizard) will be fabricating the railings and island countertop.
- The back deck has been torn off. As well as all of the old gutters and soffits.
- The kitchen cabinets are being delivered tomorrow May 1. Luis will be installing them tomorrow or Friday!
- The tile is almost all delivered.....damn ants. Tile guy is starting his prep work tomorrow.
- The millwork will hopefully be all delivered early next week with the Luis the trim carpenter starting immediately.
- The rest of the wood floors will be delivered next week and installed next Wed. May 7.